Loading...
Loading...
Create comprehensive test plans considering all test types and dependencies
npx skill4agent add wojons/skills test-planning# Generate test plans
npm run test:plan:generate # Generate comprehensive test plan
npm run test:plan:strategy # Create test strategy document
npm run test:plan:estimate # Estimate testing effort
# Feature-specific planning
npm run test:plan:feature -- "user-authentication"
npm run test:plan:release -- "v2.1.0"
# Context-aware planning
npm run test:plan -- --context mvp --type saas
npm run test:plan -- --context production --type enterprise
# Integration with project management
npm run test:plan:export -- --format jira # Jira import format
npm run test:plan:export -- --format csv # CSV for spreadsheets
npm run test:plan:export -- --format markdown # Markdown documentation
# Risk-based planning
npm run test:plan:risks # Risk assessment and planning
npm run test:plan:coverage # Test coverage planningComprehensive Test Plan
──────────────────────────────
Project: E-Commerce Platform v2.1
Stage: Beta → Production Release
Planning Date: 2024-03-15
Test Objectives:
- Validate new checkout flow functionality
- Ensure backward compatibility with existing features
- Meet performance SLAs for peak traffic
- Maintain security compliance (PCI-DSS)
- Provide confidence for production release
Test Scope:
Included:
- New checkout API and UI
- Payment gateway integration updates
- Order processing enhancements
- User notification system
Excluded:
- Legacy admin panel (separate release)
- Mobile app updates (different team)
- Third-party analytics integration
Test Approach:
Test Pyramid Implementation:
- Unit Tests: 80% coverage on new code (estimated: 250 tests)
- Integration Tests: API and database integration (estimated: 75 tests)
- E2E Tests: Critical user journeys (estimated: 25 scenarios)
Specialized Testing:
- Performance: Load testing with 2000 concurrent users
- Security: PCI-DSS compliance validation
- Accessibility: WCAG 2.1 AA compliance
- Compatibility: Chrome, Firefox, Safari, mobile browsers
Test Schedule:
Week 1-2: Development & Unit Testing
Week 3: Integration Testing & API Validation
Week 4: E2E Testing & User Acceptance
Week 5: Performance & Security Testing
Week 6: Final Validation & Production Readiness
Resource Allocation:
- Developers: 3 (unit & integration tests)
- QA Engineers: 2 (E2E & exploratory testing)
- Performance Engineer: 1 (load testing)
- Security Specialist: 1 (compliance validation)
- Environments: Dev, CI, Staging, Performance Lab
Test Environment Requirements:
- Staging environment matching production configuration
- Test database with production-like data volume
- Payment gateway sandbox accounts
- Load testing infrastructure
- Security scanning tools
Quality Gates:
1. All unit tests pass (CI gate)
2. Integration tests 100% pass (CI gate)
3. E2E critical paths 100% pass (staging gate)
4. Performance SLAs met (performance gate)
5. No critical security vulnerabilities (security gate)
6. User acceptance sign-off (UAT gate)
Risk Assessment:
High Risk:
- Payment processing integration (mitigation: extended sandbox testing)
- Database migration (mitigation: rollback testing)
Medium Risk:
- Checkout UI changes (mitigation: extensive E2E testing)
- Performance under load (mitigation: progressive load testing)
Low Risk:
- Notification system updates (mitigation: smoke testing)
Dependencies:
- Development completion by Week 2
- Staging environment availability
- Test data preparation
- Third-party service sandbox access
- Performance testing window (off-peak hours)
Success Metrics:
- Defect detection rate > 90%
- Test automation coverage > 70%
- Mean time to defect resolution < 8 hours
- Zero critical defects in production first week
Contingency Plans:
- Schedule buffer: 1 week for unexpected issues
- Rollback procedure documented and tested
- Feature flags for gradual rollout
- Monitoring plan for production release
Deliverables:
- Test strategy document
- Test cases and automation scripts
- Test execution reports
- Defect tracking and resolution
- Release readiness assessment
- Lessons learned document