Generates a new sprint plan or updates an existing one based on the current milestone, completed work, and available capacity. Pulls context from production documents and design backlogs.
npx skill4agent add donchitos/claude-code-game-studios sprint-plannewupdatestatus--review [full|lean|solo]production/review-mode.txtlean.claude/docs/director-gates.mdproduction/milestones/production/sprints/design/gdd/production/risk-register/new# Sprint [N] -- [Start Date] to [End Date]
## Sprint Goal
[One sentence describing what this sprint achieves toward the milestone]
## Capacity
- Total days: [X]
- Buffer (20%): [Y days reserved for unplanned work]
- Available: [Z days]
## Tasks
### Must Have (Critical Path)
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria |
|----|------|-------------|-----------|-------------|-------------------|
### Should Have
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria |
|----|------|-------------|-----------|-------------|-------------------|
### Nice to Have
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria |
|----|------|-------------|-----------|-------------|-------------------|
## Carryover from Previous Sprint
| Task | Reason | New Estimate |
|------|--------|-------------|
## Risks
| Risk | Probability | Impact | Mitigation |
|------|------------|--------|------------|
## Dependencies on External Factors
- [List any external dependencies]
## Definition of Done for this Sprint
- [ ] All Must Have tasks completed
- [ ] All tasks pass acceptance criteria
- [ ] QA plan exists (`production/qa/qa-plan-sprint-[N].md`)
- [ ] All Logic/Integration stories have passing unit/integration tests
- [ ] Smoke check passed (`/smoke-check sprint`)
- [ ] QA sign-off report: APPROVED or APPROVED WITH CONDITIONS (`/team-qa sprint`)
- [ ] No S1 or S2 bugs in delivered features
- [ ] Design documents updated for any deviations
- [ ] Code reviewed and mergedstatus# Sprint [N] Status -- [Date]
## Progress: [X/Y tasks complete] ([Z%])
### Completed
| Task | Completed By | Notes |
|------|-------------|-------|
### In Progress
| Task | Owner | % Done | Blockers |
|------|-------|--------|----------|
### Not Started
| Task | Owner | At Risk? | Notes |
|------|-------|----------|-------|
### Blocked
| Task | Blocker | Owner of Blocker | ETA |
|------|---------|-----------------|-----|
## Burndown Assessment
[On track / Behind / Ahead]
[If behind: What is being cut or deferred]
## Emerging Risks
- [Any new risks identified this sprint]production/sprint-status.yaml/sprint-status/story-done/helpproduction/sprint-status.yaml# Auto-generated by /sprint-plan. Updated by /story-done.
# DO NOT edit manually — use /story-done to update story status.
sprint: [N]
goal: "[sprint goal]"
start: "[YYYY-MM-DD]"
end: "[YYYY-MM-DD]"
generated: "[YYYY-MM-DD]"
updated: "[YYYY-MM-DD]"
stories:
- id: "[epic-story, e.g. 1-1]"
name: "[story name]"
file: "[production/stories/path.md]"
priority: must-have # must-have | should-have | nice-to-have
status: ready-for-dev # backlog | ready-for-dev | in-progress | review | done | blocked
owner: ""
estimate_days: 0
blocker: ""
completed: ""priority: must-havestatus: ready-for-devpriority: should-havestatus: backlogpriority: nice-to-havestatus: backlogupdatesprint-status.yamlsololeanfullproducer.claude/docs/director-gates.mdproduction/sprints/sprint-[N].mdScope check: If this sprint includes stories added beyond the original epic scope, runto detect scope creep before implementation begins./scope-check [epic]
Globproduction/qa/qa-plan-sprint-[N].mdproduction/qa/[path]"This sprint has no QA plan. A sprint plan without a QA plan means test requirements are undefined — developers won't know what 'done' looks like from a QA perspective, and the sprint cannot pass the Production → Polish gate without one.Runnow, before starting any implementation. It takes one session and produces the test case requirements each story needs."/qa-plan sprint
AskUserQuestion[A] Run /qa-plan sprint now — I'll do that before starting implementation (Recommended)[B] Skip for now — I understand QA sign-off will be blocked at the Production → Polish gate/qa-plan sprint> ⚠️ **No QA Plan**: This sprint was started without a QA plan. Run `/qa-plan sprint`
> before the last story is implemented. The Production → Polish gate requires a QA
> sign-off report, which requires a QA plan./qa-plan sprint/story-readiness [story-file]/dev-story [story-file]/sprint-status/scope-check [epic]