milestone-review

Original🇺🇸 English
Translated

Generates a comprehensive milestone progress review including feature completeness, quality metrics, risk assessment, and go/no-go recommendation. Use at milestone checkpoints or when evaluating readiness for a milestone deadline.

93installs
Added on

NPX Install

npx skill4agent add donchitos/claude-code-game-studios milestone-review

Phase 0: Parse Arguments

Extract the milestone name (
current
or a specific name) and resolve the review mode (once, store for all gate spawns this run):
  1. If
    --review [full|lean|solo]
    was passed → use that
  2. Else read
    production/review-mode.txt
    → use that value
  3. Else → default to
    lean
See
.claude/docs/director-gates.md
for the full check pattern.

Phase 1: Load Milestone Data

Read the milestone definition from
production/milestones/
. If the argument is
current
, use the most recently modified milestone file.
Read all sprint reports for sprints within this milestone from
production/sprints/
.

Phase 2: Scan Codebase Health

  • Scan for
    TODO
    ,
    FIXME
    ,
    HACK
    markers that indicate incomplete work
  • Check the risk register at
    production/risk-register/

Phase 3: Generate the Milestone Review

markdown
# Milestone Review: [Milestone Name]

## Overview
- **Target Date**: [Date]
- **Current Date**: [Today]
- **Days Remaining**: [N]
- **Sprints Completed**: [X/Y]

## Feature Completeness

### Fully Complete
| Feature | Acceptance Criteria | Test Status |
|---------|-------------------|-------------|

### Partially Complete
| Feature | % Done | Remaining Work | Risk to Milestone |
|---------|--------|---------------|------------------|

### Not Started
| Feature | Priority | Can Cut? | Impact of Cutting |
|---------|----------|----------|------------------|

## Quality Metrics
- **Open S1 Bugs**: [N] -- [List]
- **Open S2 Bugs**: [N]
- **Open S3 Bugs**: [N]
- **Test Coverage**: [X%]
- **Performance**: [Within budget? Details]

## Code Health
- **TODO count**: [N across codebase]
- **FIXME count**: [N]
- **HACK count**: [N]
- **Technical debt items**: [List critical ones]

## Risk Assessment
| Risk | Status | Impact if Realized | Mitigation Status |
|------|--------|-------------------|------------------|

## Velocity Analysis
- **Planned vs Completed** (across all sprints): [X/Y tasks = Z%]
- **Trend**: [Improving / Stable / Declining]
- **Adjusted estimate for remaining work**: [Days needed at current velocity]

## Scope Recommendations
### Protect (Must ship with milestone)
- [Feature and why]

### At Risk (May need to cut or simplify)
- [Feature and risk]

### Cut Candidates (Can defer without compromising milestone)
- [Feature and impact of cutting]

## Go/No-Go Assessment

**Recommendation**: [GO / CONDITIONAL GO / NO-GO]

**Conditions** (if conditional):
- [Condition 1 that must be met]
- [Condition 2 that must be met]

**Rationale**: [Explanation of the recommendation]

## Action Items
| # | Action | Owner | Deadline |
|---|--------|-------|----------|

Phase 3b: Producer Risk Assessment

Review mode check — apply before spawning PR-MILESTONE:
  • solo
    → skip. Note: "PR-MILESTONE skipped — Solo mode." Present the Go/No-Go section without a producer verdict.
  • lean
    → skip (not a PHASE-GATE). Note: "PR-MILESTONE skipped — Lean mode." Present the Go/No-Go section without a producer verdict.
  • full
    → spawn as normal.
Before generating the Go/No-Go recommendation, spawn
producer
via Task using gate PR-MILESTONE (
.claude/docs/director-gates.md
).
Pass: milestone name and target date, current completion percentage, blocked story count, velocity data from sprint reports (if available), list of cut candidates.
Present the producer's assessment inline within the Go/No-Go section. The producer's verdict (ON TRACK / AT RISK / OFF TRACK) informs the overall recommendation.
If OFF TRACK, use
AskUserQuestion
before generating the recommendation:
  • Prompt: "Producer verdict: OFF TRACK. The milestone is in jeopardy. This review will recommend NO-GO. How do you want to proceed?"
  • Options:
    • [A] Accept NO-GO — generate the full review with that recommendation
    • [B] Override to CONDITIONAL GO — I'll document the accepted risks myself
    • [C] Stop — I want to address blockers before generating the review
If AT RISK, use
AskUserQuestion
:
  • Prompt: "Producer verdict: AT RISK. Milestone may slip. How should the Go/No-Go section be framed?"
  • Options:
    • [A] CONDITIONAL GO — include producer's conditions in the review
    • [B] NO-GO — conditions cannot be met in time
    • [C] GO — I accept the risk and want to proceed
Do not issue a GO against an OFF TRACK verdict unless the user explicitly selects [B] above.

Phase 4: Save Review

Present the review to the user.
Ask: "May I write this to
production/milestones/[milestone-name]-review.md
?"
If yes, write the file, creating the directory if needed. Verdict: COMPLETE — milestone review saved.
If no, stop here. Verdict: BLOCKED — user declined write.

Phase 5: Next Steps

  • Run
    /gate-check
    for a formal phase gate verdict if this milestone marks a development phase boundary.
  • Run
    /sprint-plan
    to adjust the next sprint based on the scope recommendations above.